Miami-Dade County
The demolition is the fast part. This is the part that sets your date.
Asbestos survey, federal notice, permit review, utility disconnects, disposal. Run in the wrong order they add a month. Every figure on this page carries its source, and where the public record is silent we say so instead of guessing.
Asbestos comes first
Rule
Age is not the trigger
Renovation threshold
Who performs it
Affidavit
The notice runs ten working days
Duration
When the clock starts
Emergency
Rule 1
Rule 2
Rule 3
Rule 4
Rule 5
- Miami-Dade County — global
- Miami-Dade County — permits (PDF)
- Miami-Dade County — permits
- Florida DEP — air
- Florida DEP — sites (PDF)
- Florida DEP — sites (PDF)
Who files, and what with
Jurisdiction
Who may apply
Homeowners
First review cycle
Documents
- A current site survey from a certified surveyor, to scale, no more than 6 months old.
- DERM approval from the county.
- A tree boundary survey showing every tree on the lot, including trees in the right of way, with tree protection drawn onto the demolition plan.
- Tree protection details and specifications. The protection zone runs roughly 8 to 12 inches for every inch of trunk diameter at breast height.
- For residential and duplex properties the owner may prepare the tree survey. For commercial properties it has to come from a Florida licensed surveyor and may be up to 1 year old.
- Public Works, Environmental Resources or Zoning may ask for further documents.
The sequence
City of Miami
- 01Confirm the property sits inside city limits by its folio number. A folio beginning with 01 is a City of Miami property.
- 02Open an iBuild account, start the total or partial demolition permit application and name a main point of contact.
- 03Choose the submittal route, electronically or in person at 444 SW 2nd Ave, 4th Floor.
- 04Pay the upfront fee through the online portal using the transaction ID.
- 05Print and notarize the package, then upload it to ePlan.
- 06Name every file to the city naming convention before upload, because names cannot be changed once assigned. Documents carrying a professional seal need a digital signature.
- 07City pre-screening.
- 08Plan review by the reviewing departments.
- 09Final approval and permit issuance. The printed permit card has to stay on the job site.
- 10After the permit is issued, apply for the sewer cap sub-permit through iBuild. It is payment only, with no review.
- 11Where the demolition follows an unsafe structure violation, close the violation through the Unsafe Structures division.
Utilities
Requirement 1
Requirement 2
Requirement 3
Requirement 4
Where the debris goes
Transfer stations
| Facility | Address | C&D |
|---|---|---|
| North Dade Landfill | 21500 NW 47 Ave. | Yes |
| South Dade Landfill | 23707 SW 97th Ave. Gate A | Yes |
| Northeast Transfer Station | 18701 NE 6 Ave. | No |
| Central Transfer Station | 1150 NW 20 St. | No |
| West Transfer Station | 2900 SW 72 Ave. | No |
- $76.12 Contract rate, per ton
- $115.80 Non-contract rate, per ton
- $100.00 Asbestos disposal, per ton
- $16.66 contract, $17.30 non-contract, added to the disposal fee Transfer fee per ton for waste delivered to a regional transfer station
- $140.00 Waste tires, per ton
Fees
Authority
Effective
- 0.30% of the estimated cost of the project, minimum $15, maximum $1,926 Demolition permit fee
- Permit fee is doubled, plus $110 Demolition that follows a violation
- $100.00 per ton Asbestos disposal
- $87.85 per load, added to the disposal fee Solid waste requiring special handling
Miami-Dade County's own dollar figure for a demolition permit sits inside Implementing Order 4-63 and is not reproduced here because we have not read it off the order itself. Third-party sites quote figures between $100 and $1,000 for it; those numbers mix different fees together and should not be relied on.